Progress Updates

     
    November 19, 2007 Progress Update
       
    Upcoming Events
   

Friday, January 18th from 12:00 - 2:00 p.m. Cabins LCA (homeowner's association) kick-off organizational meeting for all Cabin Owners. The meeting will be held at the Suncadia Bellevue Sales Office (click here for printable directions).  Lunch will be provided. All Cabin owners are encouraged to attend.  Please r.s.v.p. to Brian Frederick: b_frederick@mac.com.

     
    Landscaping
    Hydroseeding around completed Cabins and the lake is finished. New native Douglas Firs, Ponderosa Pines and vine maple tress have been planted throughout the common areas of the neighborhood.
     
    Visitor Parking at The Cabins
    Visitor parking is available along Tumble Creek Drive and also along Sasse Lane.  http://www.opusattumblecreek.com/site_plan.htm
     
    Progress Update
    Cabins 2, 6, 7, 9, 10, 11, 12, 13, 14, 15, 16, 18 and 21 are complete. Cabin 8 will follow. Cabins 3 and 19 have been painted. Cabin 17 is being painted. Millwork is in progress on Cabin 19. Cabins 4 and 34 are fully framed with windows installed. Cabin 4 is in MEP rough-in. Plumbing rough-in has started in Cabin 34. Cabin 5 is being insulated with drywall to follow. Cabin 1 framing is complete. Roof framing is in progress on Cabins 30 and 32.
     