As you may have noticed, the
weather has been a bit warmer in the past few weeks,
which is good news for The Cabins! Progress has been
very steady since the snow has let up a little.
Cabins 10, 11, 12, 13, 14,
15, 16, 18 and 21 are completely framed. Windows are
installed in all of these units except for 14 and 16.
Insulation has started in Cabins 11 and 21 with drywall
to follow. Insulation, drywall and painting are complete
in Cabins 12, 13, and 15. Doors and millwork have
started in cabins 12 and 15 and is nearly complete in
Cabin 13. Cabins 2, 6, 7, 8 and 9 are framed through the
second floor. Cabins 3, 19 and 20 are framed through the
first floor. Cabins 4 and 17 have begun framing.
Foundation and chimney for Cabin 5 is complete with a
first floor deck and winter tarp installed. Foundations
are complete for Cabins 1 and 34 with chimney work
progressing.